  3. Percentage of Completion vs Completed Contract: How Contractors Should Show Revenue in the Books

ContractorsPercentage of Completion vs Completed Contract: How Contractors Should Show Revenue in the Books

Percentage of completion or completed contract? What each method does to your contractor P&L, a worked example with over- and under-billing, how ASC 606 fits, and which one lenders and sureties expect.

By Umaima WaheedUpdated

The short answer6 min read

Percentage of completion records revenue and profit as the work progresses, usually based on how much of the job's estimated cost you've spent so far. Completed contract records nothing until the job is finished, then records all of it at once. Percentage of completion gives a truer monthly picture of a contractor with long jobs, and it's the approach behind the WIP schedule that banks and bonding companies ask for. Completed contract is simpler but makes profit jump around and hides problems until a job closes.

Read the full answer

A note before you read: This page is about your financial statements: how revenue shows up on the P&L and balance sheet you use to run the business and share with lenders and sureties. How you report for tax can be different and is a question for your CPA. ABFI doesn't prepare taxes.

Why this matters more than it sounds

A contractor's P&L can tell two completely different stories about the same month, depending on the method. Imagine a $500,000 job that runs from September to March. Under completed contract, your fall statements show costs going out the door with almost no revenue against them, then March shows a huge profit. Under percentage of completion, each month shows its share of revenue and profit as the work happens.

If you're deciding whether to hire, bid more work or buy equipment, the second picture is the one you can act on.

The two methods in plain language

Percentage of completion. Each month, you estimate how far along each job is, then record that share of the contract's revenue. The most common way to measure progress is cost-to-cost: costs spent to date divided by total estimated costs.

Completed contract. You hold costs on the balance sheet as work in progress and record no revenue or profit until the job is substantially complete. Then you move everything to the P&L at once.

Side by side

Percentage of completionCompleted contract
When revenue shows upAs the work progressesWhen the job is finished
Monthly P&LSmoother, matches the work doneLumpy, jumps when jobs close
NeedsGood cost estimates and job costingTracking costs by job
Shows problem jobsEarly, as estimates changeLate, often at the end
What lenders and sureties expectUsually this, with a WIP scheduleLess useful to them for long jobs
Best fitJobs that span months or cross a year endVery short jobs, or very small contractors

A worked example

Here's one job, with round numbers made up for the example.

  • Contract price: $500,000
  • Estimated total cost: $400,000, so estimated gross profit is $100,000
  • Costs spent to date at month end: $160,000
  • Amount billed to the customer to date: $230,000

Percentage of completion (cost-to-cost):

  1. Percent complete = $160,000 ÷ $400,000 = 40%
  2. Revenue earned to date = 40% × $500,000 = $200,000
  3. Gross profit to date = $200,000 − $160,000 = $40,000
  4. You've billed $230,000 but only earned $200,000, so you're over-billed by $30,000. That $30,000 sits on the balance sheet as a liability (often called "billings in excess of costs and estimated earnings"), because you've collected for work you haven't done yet.

If you'd billed only $170,000, you'd be under-billed by $30,000, which shows as an asset: work done that you haven't invoiced yet.

Completed contract:

  1. Revenue to date: $0
  2. Gross profit to date: $0
  3. The $160,000 of costs sits on the balance sheet as work in progress, and the $230,000 billed sits against it as billings. Nothing reaches the P&L until the job is done.

Same job, same month. One method shows $40,000 of profit you've genuinely earned. The other shows none.

Our WIP schedule guide walks through over- and under-billing across a whole list of jobs.

What about a job that's losing money?

Under either method, when you can see a job will lose money overall, the expected loss should be recorded as soon as you know it, not spread out or saved for the end. This is one of the main reasons good estimates matter: a job that quietly slides from profit to loss should show up in the books the month it happens.

Where ASC 606 fits

ASC 606 is the US accounting standard for revenue from contracts with customers, and it applies to private companies that follow GAAP [1]. It doesn't use the names "percentage of completion" or "completed contract". Instead it asks whether you transfer control of the work to the customer over time or at a single point in time [1].

For most construction work done on a customer's property, control passes as you build, so revenue is recognized over time, measured by progress. In practice that usually looks like percentage of completion with cost-to-cost [1]. Recognizing everything at the end is only appropriate when the over-time criteria aren't met. If your statements need to follow GAAP, for a bank covenant, a surety or an audit, your outside accountant will tell you which applies to your contracts.

Which method should you use?

  • Jobs longer than a month or two, or crossing a year end: percentage of completion gives a truer picture.
  • You have a line of credit, bonding or a lender asking for a WIP schedule: percentage of completion, because that's what they're reading.
  • Very small jobs that start and finish within the month: the two methods give nearly the same answer, so simplicity wins.

Whichever you use, your books need to be on accrual, not cash: accrual vs cash accounting.

What you need in place for percentage of completion

  1. Job costing that's actually right. Every labor hour, material purchase and sub invoice coded to the right job. See job costing for contractors and our click-by-click job costing setup in QuickBooks Online.
  2. Current cost estimates. The project manager updates the estimate to complete each month. Stale estimates make the percentages wrong.
  3. A chart of accounts built for it, with balance sheet accounts for over-billings and under-billings. See chart of accounts for contractors.
  4. A monthly WIP schedule and one adjusting entry per month to bring revenue in line with it.
  5. A clean handoff to your CPA at year end: bookkeeper and CPA handoff.

Software matters too. QuickBooks Online handles job costing well for many contractors, while larger firms may need construction-specific software. Compare options in best accounting software for contractors.

Keep reading

Sources

  1. FASB, Accounting Standards Codification Topic 606, Revenue from Contracts with Customers, asc.fasb.org/606. Checked November 6, 2026.

Questions owners ask

What is the percentage of completion method?

A way to record a job's revenue and profit as the work progresses, usually by comparing costs spent so far with total estimated costs.

What is the completed contract method?

A way to record no revenue or profit on a job until it's finished, holding costs on the balance sheet as work in progress until then.

Which method do banks and bonding companies want?

Usually percentage of completion, with a monthly or quarterly WIP schedule, because it shows earned profit and over- or under-billing on every open job.

Is completed contract allowed under GAAP?

ASC 606 doesn't use that name. It asks whether revenue is earned over time or at a point in time. Most construction on a customer's property is recognized over time, which looks like percentage of completion. Ask your outside accountant how it applies to your contracts.

How often should I update percentage of completion?

Every month, at the close. Update each job's estimate to complete, rerun the WIP schedule and post one adjusting entry so revenue matches the work done.

Want a WIP schedule your banker trusts?

ABFI sets up job costing, runs your monthly WIP schedule and closes your books on accrual. Start with a complimentary Business Accounting Diagnostic.